--- name: scope-check description: "Analyze a feature or sprint for scope creep by comparing current scope against the original plan. Flags additions, quantifies bloat, and recommends cuts." argument-hint: "[feature-name or sprint-N]" user-invocable: true allowed-tools: Read, Glob, Grep context: | !git diff --stat HEAD~20 2>/dev/null --- When this skill is invoked: 1. **Read the original plan** — Find the relevant document: - If a feature name: read the design doc from `design/gdd/` - If a sprint number: read the sprint plan from `production/sprints/` - If a milestone: read the milestone definition from `production/milestones/` 2. **Read the current state** — Check what has actually been implemented or is in progress: - Scan the codebase for files related to the feature/sprint - Read git log for commits related to this work - Check for TODO comments that indicate unfinished scope additions 3. **Compare original vs current scope**: ```markdown ## Scope Check: [Feature/Sprint Name] Generated: [Date] ### Original Scope [List of items from the original plan] ### Current Scope [List of items currently implemented or in progress] ### Scope Additions (not in original plan) | Addition | Who Added | When | Justified? | Effort | |----------|-----------|------|------------|--------| | [item] | [commit/person] | [date] | [Yes/No/Unclear] | [S/M/L] | ### Scope Removals (in original but dropped) | Removed Item | Reason | Impact | |-------------|--------|--------| | [item] | [why removed] | [what's affected] | ### Bloat Score - Original items: [N] - Current items: [N] - Items added: [N] (+[X]%) - Items removed: [N] - Net scope change: [+/-N] ([X]%) ### Risk Assessment - **Schedule Risk**: [Low/Medium/High] — [explanation] - **Quality Risk**: [Low/Medium/High] — [explanation] - **Integration Risk**: [Low/Medium/High] — [explanation] ### Recommendations 1. **Cut**: [Items that should be removed to stay on schedule] 2. **Defer**: [Items that can move to a future sprint/version] 3. **Keep**: [Additions that are genuinely necessary] 4. **Flag**: [Items that need a decision from producer/creative-director] ``` 4. **Output the scope check** with a clear verdict: - **On Track**: Scope within 10% of original - **Minor Creep**: 10-25% scope increase — manageable with adjustments - **Significant Creep**: 25-50% scope increase — need to cut or extend timeline - **Out of Control**: >50% scope increase — stop and re-plan ### Rules - Scope creep is additions without corresponding cuts or timeline extensions - Not all additions are bad — some are discovered requirements. But they must be acknowledged and accounted for. - When recommending cuts, prioritize preserving the core player experience over nice-to-haves - Always quantify scope changes — "it feels bigger" is not actionable, "+35% items" is