Files
Claude-Code-Game-Studios/.claude/skills/sprint-plan/SKILL.md
Donchitos 70fbf670fc Gap closure: feedback loops, traceability, and new /content-audit skill
- NEW /content-audit skill: GDD-specified content vs implemented content gap
  report with COMPLETE/IN PROGRESS/EARLY/NOT STARTED per system
- balance-check: Fix & Verify Cycle phase (fix → re-verify → propagate-design-change)
- perf-profile: Scope & Timeline Decision phase for M/L effort optimizations
- playtest-report: Action Routing phase categorizes findings → design/balance/bugs/polish
- review-all-gdds: Phase 4 Cross-System Scenario Walkthrough (multi-system sequences)
- story-done: Test-Criterion Traceability (each AC mapped to a test, BLOCKING if >50% untested)
- code-review: ADR Compliance Check (ARCHITECTURAL VIOLATION / ADR DRIFT / MINOR DEVIATION)
- setup-engine: upgrade subcommand (pre-upgrade API scan, migration plan, VERSION.md update)
- story-readiness: Asset References Check (verifies referenced asset paths exist)
- validate-assets.sh: invalid JSON now exits 1 (blocking); naming issues exit 0 (warning)
- workflow-catalog.yaml + sprint-plan: /scope-check wired into production phase

Co-Authored-By: Claude Sonnet 4.6 <noreply@anthropic.com>
2026-03-12 11:18:43 +11:00

4.7 KiB

name, description, argument-hint, user-invocable, allowed-tools, context
name description argument-hint user-invocable allowed-tools context
sprint-plan Generates a new sprint plan or updates an existing one based on the current milestone, completed work, and available capacity. Pulls context from production documents and design backlogs. [new|update|status] true Read, Glob, Grep, Write, Edit !ls production/sprints/ 2>/dev/null

When this skill is invoked:

  1. Read the current milestone from production/milestones/.

  2. Read the previous sprint (if any) from production/sprints/ to understand velocity and carryover.

  3. Scan design documents in design/gdd/ for features tagged as ready for implementation.

  4. Check the risk register at production/risk-register/.

For new:

  1. Generate a sprint plan following this format:
# Sprint [N] -- [Start Date] to [End Date]

## Sprint Goal
[One sentence describing what this sprint achieves toward the milestone]

## Capacity
- Total days: [X]
- Buffer (20%): [Y days reserved for unplanned work]
- Available: [Z days]

## Tasks

### Must Have (Critical Path)
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

### Should Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

### Nice to Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria |
|----|------|-------------|-----------|-------------|-------------------|

## Carryover from Previous Sprint
| Task | Reason | New Estimate |
|------|--------|-------------|

## Risks
| Risk | Probability | Impact | Mitigation |
|------|------------|--------|------------|

## Dependencies on External Factors
- [List any external dependencies]

## Definition of Done for this Sprint
- [ ] All Must Have tasks completed
- [ ] All tasks pass acceptance criteria
- [ ] No S1 or S2 bugs in delivered features
- [ ] Design documents updated for any deviations
- [ ] Code reviewed and merged

For status:

  1. Generate a status report:
# Sprint [N] Status -- [Date]

## Progress: [X/Y tasks complete] ([Z%])

### Completed
| Task | Completed By | Notes |
|------|-------------|-------|

### In Progress
| Task | Owner | % Done | Blockers |
|------|-------|--------|----------|

### Not Started
| Task | Owner | At Risk? | Notes |
|------|-------|----------|-------|

### Blocked
| Task | Blocker | Owner of Blocker | ETA |
|------|---------|-----------------|-----|

## Burndown Assessment
[On track / Behind / Ahead]
[If behind: What is being cut or deferred]

## Emerging Risks
- [Any new risks identified this sprint]

Sprint Status File

After generating a new sprint plan, also write production/sprint-status.yaml. This is the machine-readable source of truth for story status — read by /sprint-status, /story-done, and /help without markdown parsing.

Ask: "May I also write production/sprint-status.yaml to track story status?"

Format:

# Auto-generated by /sprint-plan. Updated by /story-done.
# DO NOT edit manually — use /story-done to update story status.

sprint: [N]
goal: "[sprint goal]"
start: "[YYYY-MM-DD]"
end: "[YYYY-MM-DD]"
generated: "[YYYY-MM-DD]"
updated: "[YYYY-MM-DD]"

stories:
  - id: "[epic-story, e.g. 1-1]"
    name: "[story name]"
    file: "[production/stories/path.md]"
    priority: must-have        # must-have | should-have | nice-to-have
    status: ready-for-dev      # backlog | ready-for-dev | in-progress | review | done | blocked
    owner: ""
    estimate_days: 0
    blocker: ""
    completed: ""

Initialize each story from the sprint plan's task tables:

  • Must Have tasks → priority: must-have, status: ready-for-dev
  • Should Have tasks → priority: should-have, status: backlog
  • Nice to Have tasks → priority: nice-to-have, status: backlog

For update: read the existing sprint-status.yaml, carry over statuses for stories that haven't changed, add new stories, remove dropped ones.

Scope Reminder

After presenting the sprint plan, add:

Scope check: If this sprint includes stories added beyond the original epic scope, run /scope-check [epic] to detect scope creep before implementation begins.

When reviewing stories during selection (step 3 above), note any stories that appear outside the original epic goals. If any are uncertain, flag them inline: "Are these stories within the original epic scope? If unsure, /scope-check can verify."

Agent Consultation

For comprehensive sprint planning, consider consulting:

  • producer agent for capacity planning, risk assessment, and cross-department coordination
  • game-designer agent for feature prioritization and design readiness assessment