Fix release for 1.1.2: the 14 longest skills keep their later phases after a compaction, a question nobody answered is never taken as an answer, settings read the same from a subfolder, the commit check works for a project in a subfolder of a larger repository, every skill opens with a title, and the shipped allow rules no longer approve deleting a branch or writing files without asking. Details in CHANGELOG.md; upgrade steps in UPGRADING.md (v1.1.2 → v1.1.3). Refs #83 Refs #133 Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_0185en4t76fPn7315q4c3nko
255 lines
11 KiB
Markdown
255 lines
11 KiB
Markdown
---
|
|
name: milestone-review
|
|
description: "Milestone progress review — completeness, quality metrics, risk, go/no-go recommendation. At checkpoints or before a deadline."
|
|
argument-hint: "[milestone-name|current] [--review full|lean|solo]"
|
|
user-invocable: true
|
|
allowed-tools: Read, Glob, Grep, Write, Agent, AskUserQuestion, Bash(bash "*/.claude/skills/milestone-review/../../hooks/yaml-helper.sh" resolve_config *)
|
|
model: sonnet
|
|
---
|
|
|
|
!`bash "${CLAUDE_SKILL_DIR}/../../hooks/yaml-helper.sh" resolve_config --keys review_mode,automation,workflow`
|
|
|
|
Resolved above — use as-is; `--review` overrides `review_mode` for this run. No
|
|
block → defaults in `.claude/docs/config-resolution.md`.
|
|
|
|
# Milestone Review
|
|
|
|
|
|
|
|
## Insufficient input — check this before producing any report
|
|
|
|
**If the inputs this skill needs do not exist, the answer is "could not run" —
|
|
not a filled-in report.** Check first, and stop if the check fails.
|
|
|
|
1. List the inputs this skill reads (data files, prior reports, profiler output,
|
|
test results, registries, source code).
|
|
2. For each, record `FOUND` or `ABSENT` — not "assumed present".
|
|
3. If any input required for a section is ABSENT, that section is
|
|
**`NOT ASSESSED — NO DATA`**. Do not estimate it, do not infer it from an
|
|
adjacent artifact, and do not leave a mandated cell to be filled by whoever
|
|
reads the template next.
|
|
4. If **every** required input is ABSENT, stop and report
|
|
**`NOT ASSESSED — NO DATA`** as the whole verdict, naming what was missing and
|
|
which skill produces it.
|
|
|
|
**A verdict of `NOT ASSESSED` is a success.** It is the correct, useful answer to
|
|
"what does the data say?" when there is no data. The failure mode this prevents is
|
|
specific: a report whose verdict enum has no "could not run" state produces
|
|
**false clean passes** — an asset audit returning COMPLIANT on a project with no
|
|
assets and no standards, or a performance profile reporting ">99% headroom against
|
|
a 16.67ms budget" with zero profiler data and no budget ever set.
|
|
|
|
**Absence of evidence is never evidence of absence.** A scan that finds no
|
|
matches because there are no files to scan has not verified anything. Say which of
|
|
the two happened — a reader cannot tell from a green result.
|
|
|
|
---
|
|
|
|
## Phase 0: Parse Arguments
|
|
|
|
Extract the milestone name (`current` or a specific name).
|
|
|
|
See `.claude/docs/director-gates.md` for the full check pattern. Individual gate definitions live in `.claude/docs/director-gates/[gate-id].md` — the spawned agent reads its own gate file; do not read it in the parent session.
|
|
|
|
|
|
Every `AskUserQuestion` call follows `.claude/docs/automation-modes.md`
|
|
(collaborative asks always · guided major-only · autonomous logs and proceeds;
|
|
`automation_always_ask` categories always prompt).
|
|
|
|
---
|
|
|
|
## Phase 1: Load Milestone Data
|
|
|
|
Read the milestone definition from `production/milestones/` if it exists. If the
|
|
argument is `current`, use the most recently modified milestone file.
|
|
|
|
> **No skill writes `production/milestones/`** — definitions are authored by hand
|
|
> from `.claude/docs/templates/milestone-definition.md`, so most projects have
|
|
> none. When the directory is absent or empty, say so and review against the
|
|
> sprint reports alone; do not fabricate a definition. Take care with `current`:
|
|
> this skill writes its own output as `[milestone-name]-review.md`, so a
|
|
> most-recently-modified match can be a previous *review* rather than a
|
|
> definition. Skip files ending `-review.md` when selecting.
|
|
|
|
Gather the sprint reports for sprints within this milestone from
|
|
`production/sprints/`. Establish the denominator (glob them, count **N**), then
|
|
scan the sections a milestone review actually aggregates rather than reading each
|
|
report whole:
|
|
|
|
```
|
|
Grep pattern="^## (Sprint Goal|Capacity|Tasks|Carryover|Risks|Progress|Burndown Assessment|Emerging Risks|Definition of Done)" glob="production/sprints/sprint-*.md" output_mode="content" -A 12
|
|
```
|
|
|
|
> **These alternates are copied from `/sprint-plan`'s emitted headings — keep
|
|
> them in sync with it, not with what a milestone review wishes existed.** The
|
|
> previous pattern asked for `Summary|Goal|Velocity|Completed|Blockers|
|
|
> Retrospective`, none of which `/sprint-plan` writes (it emits `## Sprint
|
|
> Goal`, not `## Goal`). Only `Carryover` matched — and that was the trap: a
|
|
> non-zero match count meant the zero-match escape hatch below could never
|
|
> fire, so every milestone review silently aggregated carryover tables and
|
|
> nothing else while reporting full coverage.
|
|
|
|
Full-read a single sprint report when its scanned sections point outside
|
|
themselves, or when it matched nothing — a zero-match report predates the
|
|
template and must be read, never silently dropped from the milestone's history.
|
|
Report any sprint that contributed nothing: a milestone summary that quietly
|
|
omits a sprint understates the work and the slippage both.
|
|
|
|
**Blocked stories** — the Blocked table and the blocked story count passed to
|
|
PR-MILESTONE — are not in the sprint reports' scanned sections. Read them where
|
|
they are recorded: the `status: blocked` stories in `production/sprint-status.yaml`
|
|
(with their `blocker` field) and, for stories outside that sprint, one grep:
|
|
|
|
```
|
|
Grep pattern="^> \*\*Status\*\*: Blocked|BLOCKED:" glob="production/epics/**/story-*.md" output_mode="content"
|
|
```
|
|
|
|
Each blocked story goes in the Blocked table under the feature its epic folder
|
|
implements, with its blocker (the yaml `blocker` field or the story's `BLOCKED:`
|
|
note). With no story files and no `sprint-status.yaml`, the Blocked table and the
|
|
blocked story count are `NOT ASSESSED — NO DATA`, not zero.
|
|
|
|
---
|
|
|
|
## Phase 2: Scan Codebase Health
|
|
|
|
- Scan for `TODO`, `FIXME`, `HACK` markers that indicate incomplete work
|
|
- Count open bugs by severity for Quality Metrics from `production/qa/bugs/` (one grep of the `**Severity**` and `**Status**` lines, as `/bug-triage` does); with no bug files, the bug lines are `NOT ASSESSED — NO DATA`, not zero
|
|
- Check the risk register at `production/risk-register/` if it exists (hand-authored from `.claude/docs/templates/risk-register-entry.md`; no skill writes it, so absence is normal — note it rather than skipping risk assessment silently)
|
|
|
|
---
|
|
|
|
## Phase 3: Generate the Milestone Review
|
|
|
|
```markdown
|
|
# Milestone Review: [Milestone Name]
|
|
|
|
## Overview
|
|
- **Target Date**: [Date]
|
|
- **Current Date**: [Today]
|
|
- **Days Remaining**: [N]
|
|
- **Sprints Completed**: [X/Y]
|
|
|
|
## Feature Completeness
|
|
|
|
### Fully Complete
|
|
Only a feature whose Status is `Complete` goes here or counts toward the completion percentage; a Deferred feature stays in its denominator, named with the milestone it moved to.
|
|
|
|
| Feature | Acceptance Criteria | Test Status |
|
|
|---------|-------------------|-------------|
|
|
|
|
### Partially Complete
|
|
| Feature | % Done | Remaining Work | Risk to Milestone |
|
|
|---------|--------|---------------|------------------|
|
|
|
|
### Blocked
|
|
A started feature whose stories are Blocked goes here, not under Partially
|
|
Complete — name the blocker, so the review says why it stalled, not only that
|
|
the count moved.
|
|
|
|
| Feature | Blocked Stories | Blocker | Next Action / Owner |
|
|
|---------|----------------|---------|---------------------|
|
|
|
|
### Not Started
|
|
| Feature | Priority | Can Cut? | Impact of Cutting |
|
|
|---------|----------|----------|------------------|
|
|
|
|
## Quality Metrics
|
|
- **Open S1 Bugs**: [N] -- [List]
|
|
- **Open S2 Bugs**: [N]
|
|
- **Open S3 Bugs**: [N]
|
|
- **Test Coverage**: [X%]
|
|
- **Performance**: [Within budget? Details]
|
|
|
|
## Code Health
|
|
- **TODO count**: [N across codebase]
|
|
- **FIXME count**: [N]
|
|
- **HACK count**: [N]
|
|
- **Technical debt items**: [List critical ones]
|
|
|
|
## Risk Assessment
|
|
| Risk | Status | Impact if Realized | Mitigation Status |
|
|
|------|--------|-------------------|------------------|
|
|
|
|
## Velocity Analysis
|
|
- **Planned vs Completed** (across all sprints): [X/Y tasks = Z%]
|
|
- **Trend**: [Improving / Stable / Declining]
|
|
- **Adjusted estimate for remaining work**: [Days needed at current velocity]
|
|
|
|
## Scope Recommendations
|
|
### Protect (Must ship with milestone)
|
|
- [Feature and why]
|
|
|
|
### At Risk (May need to cut or simplify)
|
|
- [Feature and risk]
|
|
|
|
### Cut Candidates (Can defer without compromising milestone)
|
|
- [Feature and impact of cutting]
|
|
|
|
## Go/No-Go Assessment
|
|
|
|
**Recommendation**: [NOT ASSESSED / GO / CONDITIONAL GO / NO-GO]
|
|
|
|
**Conditions** (if conditional):
|
|
- [Condition 1 that must be met]
|
|
- [Condition 2 that must be met]
|
|
|
|
**Rationale**: [Explanation of the recommendation]
|
|
|
|
## Action Items
|
|
| # | Action | Owner | Deadline |
|
|
|---|--------|-------|----------|
|
|
```
|
|
|
|
---
|
|
|
|
## Phase 3b: Producer Risk Assessment
|
|
|
|
**Review mode check** — apply before spawning PR-MILESTONE:
|
|
- `solo` → skip. Note: "PR-MILESTONE skipped — Solo mode." Present the Go/No-Go section without a producer verdict.
|
|
- `lean` → skip (not a PHASE-GATE). Note: "PR-MILESTONE skipped — Lean mode." Present the Go/No-Go section without a producer verdict.
|
|
- `full` → spawn as normal.
|
|
|
|
Before generating the Go/No-Go recommendation, spawn `producer` via `Agent` using gate **PR-MILESTONE** (`.claude/docs/director-gates/pr-milestone.md`).
|
|
|
|
Pass: milestone name and target date, current completion percentage, blocked story count, velocity data from sprint reports (if available), list of cut candidates.
|
|
|
|
Present the producer's assessment inline within the Go/No-Go section. The producer's verdict (ON TRACK / AT RISK / OFF TRACK) informs the overall recommendation.
|
|
|
|
If OFF TRACK, use `AskUserQuestion` before generating the recommendation:
|
|
- Prompt: "Producer verdict: OFF TRACK. The milestone is in jeopardy. This review will recommend NO-GO. How do you want to proceed?"
|
|
- Options:
|
|
- `[A] Accept NO-GO — generate the full review with that recommendation`
|
|
- `[B] Override to CONDITIONAL GO — I'll document the accepted risks myself`
|
|
- `[C] Stop — I want to address blockers before generating the review`
|
|
|
|
If AT RISK, use `AskUserQuestion`:
|
|
- Prompt: "Producer verdict: AT RISK. Milestone may slip. How should the Go/No-Go section be framed?"
|
|
- Options:
|
|
- `[A] CONDITIONAL GO — include producer's conditions in the review`
|
|
- `[B] NO-GO — conditions cannot be met in time`
|
|
- `[C] GO — I accept the risk and want to proceed`
|
|
|
|
If NOT ASSESSED: name the missing input — it is not ON TRACK, and never recommend GO on it. Supply the input and re-run PR-MILESTONE, or recommend NOT ASSESSED — or CONDITIONAL GO / NO-GO where the review's own findings call for one (the rank in `.claude/docs/director-gates.md`).
|
|
|
|
Do not issue a GO against an OFF TRACK verdict; issue CONDITIONAL GO only if the user explicitly selects [B] above.
|
|
|
|
---
|
|
|
|
## Phase 4: Save Review
|
|
|
|
Present the review to the user.
|
|
|
|
Ask: "May I write this to `production/milestones/[milestone-name]-review.md`?"
|
|
|
|
If yes, write the file, creating the directory if needed. Verdict: **COMPLETE** — milestone review saved.
|
|
|
|
If no, stop here. Verdict: **BLOCKED** — user declined write.
|
|
|
|
---
|
|
|
|
## Phase 5: Next Steps
|
|
|
|
- Run `/gate-check` for a formal phase gate verdict if this milestone marks a development phase boundary.
|
|
- Run `/sprint-plan` to adjust the next sprint based on the scope recommendations above (at `workflow: minimal`, which has no sprints, adjust the brief's build order instead).
|